HomeMy WebLinkAbout06-07-2016 workshop City Council of Peachtree City
Workshop Minutes
June 7, 2016
The Mayor and Council of Peachtree City met in workshop session on Tuesday, June 7, 2016. Mayor
Fleisch opened the workshop at 6:30 p.m. Council Members attending: Terry Ernst, Mike King, Kim
Learnard, and Phil Prebor.
The purpose of the workshop was to discuss:
• City Council Goals and Objectives- FY2016 Prioritization Finale
• Discuss Spillway Replacement- Design Options, Preferences
• Discuss SPLOST Projects List
• Discuss Spillway Replacement- Design Options, Preferences
City Manager Jon Rorie said the order of the items would be changed, and the spillway
replacement would be first so it would be easier to connect everything at the end.
Dan Davis, Integrated Science & Engineering (ISE), reported that the team had crafted a work plan
over the past two months to replace the spillway and refashion the dam, and they hoped to do the
work without having to lower the lake completely again. There was a possibility the new spillway
could be built immediately downstream from the current spillway. They planned to do the
construction during the winter months when the grass was not growing.
Davis introduced the project team for the Lake Peachtree Spillway design. In addition to Davis,
project principal, Rich Greuel of ISE, would provide program management. Leslie Baer would work
with communications. Randy Bass from Schnabel Engineering would provide the spillway design,
John Vermont from Corblu Ecology Group would take care of environmental permitting, and
Annette Bowman of Bowman Landscape Design would oversee landscaping design.
Davis continued that the permitting was not expected to be extensive because the work would fall
under the maintenance category_ The trees on the backside of the dam would be removed, and
the Community Garden would be exposed. There would be a new environment in the area.
Davis gave a brief history of spillway and dam, noting that two years ago, the Environmental
Protection Division (EPD) had categorized the dam and spillway as Category 1, but the City was
able to have the categorization changed back to Category 2. Davis continued that the dam
would be designed to a Category 1 standard so there would be no questions in the future.
Bass explained Category 1 meant, if the dam were to fail, there would be loss of life. The City
fought the reclassification and showed that no homes would have issues with water if the dam
failed, so the state changed the dam back to Category 2. Category 2 dams did not kill anyone
when the dams failed. Category 1 had stringent conditions for dams.
Bass continued that the most common deficiency for a Category 1 dam was that a spillway was
not big enough for certain flood events. The City currently had a broad-crested spillway
(approximately 150 feet wide with water flowing over it). Spillways that zigzagged, such as a piano
key or labyrinth weirs, allowed a lot more water to flow over the current 150-foot space. Bass said
the goal was to design the most cost effective spillway, which could be a combination of different
types, including a gated weir. Another goal was to not increase the water out in the lake now
during two-year to 100-year flood events. For over 100-year events, a Category 1 dam had to pass
all the water through the spillway in a hurry.
City Council Workshop Minutes
June 7,2016
Page 2
The plan was to put the new spillway in front of (south of) the current one, then the old spillway
would act as a cofferdam during construction. The lake would have to be drained a bit, Bass
continued, but not as much as would be required if they took the existing spillway out.
Bass continued that, based on preliminary calculations, the piano key weir was narrower and
should fit better in the space. There were no piano key weirs currently in the United States, but
Schnabel was currently designing one in North Carolina. The piano key weir was more efficient
than a labyrinth weir, but would cost more because of its shape. The additional cost of the
concrete had to be balanced with the efficiency of the spillway, Bass said.
If the dam had to be raised, they would build a parapet rather than bringing in more dirt for the
back side of the dam, Bass said. The type of spillway would determine whether there would be a
two to three-foot high parapet on the dam. The piano key would not require this, but a labyrinth
weir would. The City would have to decide if they wanted to be regulated by the state or try to
maintain Category 2 status even though the dam would be built to Category 1 standards.
Vermont said the good news was that the Corps of Engineers said the current dam was serviceable
and there was a nationwide permit for it, which was an easy set of permits that would be
inexpensive and timely, usually taking 45- 60 days. Permit 3A was a nationwide permit, renewable
every five years, which allowed for minor deviations in configuration and took into account modern
protocols and standards that would change over time. Vermont said it should easy to make an
argument for changing the broad-crested weir to a labyrinth or piano key weir as it was a safety
and efficiency upgrade. Vermont said they would have to provide a fair amount of operational
backup data to show the City was not trying to raise the lake and increase the pool area. There
were a lot of allowances under the Permit 3A.
Vermont said they were assuming they would need a stream buffer variance from the Corps,
although water supply reservoirs were exempt. The requirements for existing reservoirs with multi-
purpose uses were murky. After discussions with City staff, the City had decided to go for the
variance. Something could be triggered that would be outside the exemption while building the
temporary access and construction roads. Vermont said his role was to stay proactive in the design
process, so the City did not get too far away from the permits that were easier to obtain.
Davis noted they would be removing the-trees on the back slope,of the dam during the process.
When the trees were removed, people would be able to see into the Community Gardens.
Removing the trees was part of bringing the dam up to Category 1 standards.
King referred to the intergovernmental agreement with Fayette County regarding the lake, asking if
the County was responsible for removing the trees from the backside dam. Rorie said the County
would remove the trees near the spillway. Someone from EPD's Safe Dams program had come to
look at the trees, saying the trees should not be cut unless the upgrades were made. Learnard said
she also believed the County was responsible for removing the trees from the dam, and they could
do it a minimal cost. Rorie said they would look at the agreement.
Prebor said he did not want a gated spillway unless it was a great deal less expensive than the
others due to the maintenance requirements. He asked which spillway the team recommended
and was more cost effective. Davis said that Bass would begin working with the math equations
and modeling them on the different options for weirs, adding they were not at a point yet where a
recommendation could be made. They would be back with a recommendation.
City Council Workshop Minutes
June 7,2016
Page 3
Greuel referred to questions about the cart path, saying they could plan for a cart path bridge
over the weir that did not have to be built as part of the project. Currently, there were one-way
cart paths on either side of Kelly Drive. People driving golf carts had to cross the road to get to the
narrow path in the direction they were travelling on the bridge. The foundations for the cart path
bridge could be built as part of the design, then, when the City was ready, the bridge could be
dropped onto the foundations. Greuel said Bass would need to know what the City wanted in
order to include it on his design.
Fleisch asked if a path could be built over the dam. Greuel said it could, but it would be'a new
impact on the dam, which meant another permit process. Putting the bridge on top of the spillway
allowed the City to have two projects on one permit. Fleisch said people would not be used to 30-
foot swath of trees being gone. Having a bridge on that side would be more functional since
people could get to the Community Gardens. Greuel said that could become complicated.
Davis said one idea would be to shift the driving lanes on Mclntosh/Kelly so there was more room
on the other side. A structural engineer would need to look at it. It was worth exploring. He noted
that the Water & Sewerage Authority (WASA) had an aerial line supported on timbers in the area,
so there was an existing impact. They could work with WASA on the cart path and stronger
supports for the sewer line, so there would not be an additional impact. Vermont said that could
work with the permitting.
Annette Bowman said any successful project would take input from residents. Bowman, who
worked for the City at one time, said she had done quite a bit of work in the City as a landscape
designer. She was very sensitive to what residents wanted. It would be a safe, passive area. She
would be respectful of the engineering so the vegetation did not ruin the dam 20 years down the
road. Landscaping was a way of guiding the eye to look at certain things. The design would
include indigenous species that could handle intermittent wet feet in the low-lying areas and long
lasting trees in the higher areas. A little bit could do a whole lot when put where it mattered. The
landscaping would be the icing on the cake after the initial engineering.
Learnard asked why the trees had to be removed. Davis said the trees to be removed on the back
slope of the dam were part of the process to bring the dam up to Category 1 standards.
Prebor asked why the bridge would be on the dam side. Fleisch said if the width was very narrow, it
would not solve the existing issue. She wanted to explore the possibility of shifting the road to see if
it was feasible and whether it would be too expensive. Learnard said if the wider path were over
the spillway, they would not need the path on the other side of the road. If the road could be
shifted, there would be more room on the dam side for a wider path. Prebor said it sounded
expensive to move the path to the dam side of the road.
Ernst said the options for the spillway had been narrowed down, but he wanted to know if they
were in the ballpark with the costs. Davis said the next time they came back they would have the
preferred spillway option and a cost estimate that would include cart path options and
landscaping. Ernst clarified Council did not need to tell the design team what they wanted at this
meeting. Davis said that was correct.
Bass discussed the parapet wall on the dam, noting there would be waves during a storm event.
The top of the dam had to account for the storm surge and wave action. He continued that in the
City's case, the dam was so wide that the storm surge would not wash the dam away, but the state
would still want something so the waves would not wash over the dam. The parapet would be
there strictly for wave action and would tie into the spillway. Council was concerned that might
City Council Workshop Minutes
June 7,2016
Page 4
interfere with a cart path. Bass said it would be workable, but they were hoping they would not
need a parapet. It would depend on how the spillway was engineered.
Fleisch asked how the old spillway would be removed. Bass said there would not be any blasting.
Because they would get more water over the weir, the channel had to be wider than the spillway.
They might need to trim off the point to make the entrance channel wider, but they would not
know until the analysis was finished. The soil that came out would be used to fill depression in other
areas. The piano key weir would be an attractive nuisance, and people would stop to watch the
water flow over tf re spillway.
Davis said the spillway would be designed to Category 1 standards. In event of a breach, the
water could get close to the three homes nearby but would not displace anyone. If Council
wanted to make the additional measures to ensure safety for the residents downstream, the only
piece lacking would be an Emergency Action Plan, which would be done at the end. Rorie added
that inspections would also have to be done, and that's what had gotten the City in this position.
Learnard clarified those would be a City responsibility. Davis said they would.
Davis continued that Council could voluntarily make the dam a Category 1 dam and it would be
on the state's inspection list, but the dam they designed would meet the state's standards. Bass
said the state could change the Category 1 standards, and the City would have to make the
changes. Council consensus was to keep the dam as a Category 2 dam and to put an Emergency
Action Plan in place. Bass said that the current dam would be good and safe once the trees were
removed and the spillway was replaced. He recommended keeping it at Category 2 until the
state said otherwise.
Corrine Key Hayes said the recommendation to build the dam/spillway to Category 1 standards,
but leave it as Category 2 made a lot of sense, asking if the trees could be left where they were
until a decision was made to make the dam a Category 1. Bass explained that trees on a dam
were not good. The roots grew, and when the tree died, the roots rotted, allowing water to seep
through the dam. The trees should not be on the dam, and it was a safety concern. Hayes asked
that plenty of time be taken for the Corps permits, saying the Corps of Engineers and state
agencies tended to have long time frames. She said there was a lot of interest in a passive design
rather than an active design. She asked that the "clogging of debris" during storm events be taken
into account during the design. Bass said during a big event everything not tied down would wash
into the lake. Generally with a labyrinth or piano key weir, debris should wash over the spillway, but
it would not be uncommon for some trees/floating docks to be on the spillway. A string of buoys
could be put out on the upstream side, which would help keep debris out of the spillway, as well as
canoers and boaters.
Eric lmker said the City was doing this right. He encouraged Council to not try to shoehorn a
spillway in, but to do it right the first time. He suggested turning the current paths into a pedestrian
paths and go with a 12-foot wide cart path over the spillway.
lmker continued that in December 2014 the City was notified the category of the dam had been
changed back to Category 2. However, the state had retained the right to change the dam back
to Category 1, which was one of the reasons driving the Category 1 design. He appreciated the
efforts the City was taking. The City could purchase three homes that were the issue and eliminate
the problem of Category 1 or Category 2.
City Council Workshop Minutes
June 7,2016
Page 5
• Discuss SPLOST Projects List
Rorie said he had received feedback from Council following the June 2 regular meeting, and some
changes had been made. The estimated revenues for Peachtree City from a five-year Special
Purpose Local Option Sales Tax (SPLOST) would be $37,580,607. The estimated revenues for the City
from a six-year SPLOST would be $45,344,727. For practical purposes, the City's projects had been
based on a five-year SPLOST.
No changes were recommended in the list for Public Safety projects. Most of the items were
capital purchases. The Tier 1 projects for Public Safety included:
Project Public Safety Project Description Estimated Project Cost
Public Safety Vehicle Replacement of Medic 83 Ambulance $246,000
Personal Protective FD-Self Contained Breathing Apparatus Replacements $270,000
Equipment
Radios P25 Compliant Digital Radio Replacements for Police, Fire and Public $494,100
Works
Public Safety Vehicle Replacement of Fire Department Aerial Apparatus-Quint 84 $1,000,000
Personal Protective Police-Mobile Coban Camera Replacements-20 @$6,000 $120,000
Equipment
Public Safety Estimated Total Cost $2,130,100
Rorie continued there had been some changes in the list for Parks and Recreation. One of the
changes would be to find another name for Snake Island. The addition of a passive park would be
discussed, but it was not removed from the list. He continued that Council decided to include the
"splash pad" at Glenloch as a SPLOST project rather than in the General Fund budget. He
removed the Battery Way restrooms from the list. Tier 1 projects for Parks and Recreation now
included:
Project Parks and Recreation Project Description Estimated
Project Cost
Snake Island Development and addition of new passive park to enhance access to Lake $200,000
Peachtree
All Childrens Playground Addition of Bridge/Causeway ACP to Drake Field $250,000
Glenloch Recreation Addition of"Splash Pad"feature to Glenloch Recreational Facility $330,000
Line Creek Pork Addition of restroom facility at Line Creek Nature Area Park $150,000
10%Project Contingency $93.000
Parks and Recreation Estimated Total Costs $1,023,000
One project had been eliminated and the rest moved to Tier 2. Tier 1 Transportation projects
included:
Project Safety and Operational Intersection Estimated Project Cost
Improvements Project Description
Crosstown @ Add right turn lanes to facilitate efficient all four way stop $550,000
Peachtree Parkway intersection.
SR 54@ Intersection improvements to facilitate side street traffic movement
Planterra Way and eliminate split-phase signal to increase traffic flow along 54 $650,000
corridor
SR 54@ MacDuff Intersection improvements to facilitate side street traffic movement
Parkway and eliminate split-phase signal to increase traffic flow along 54 $650,000
corridor
SR 74@
N.Kedron Dr. Extend left turn lane capacity of N.Kedron Dr. $300,000
10%Project Contingency $215,000
Safety and Operational Intersection improvements Estimated Total Costs $2,365,000
City Council Workshop Minutes
June 7,2016
Page 6
Tier 1 Trans.ortation road resurfacing/maintenance included:
Project Road Resurfacing/Maintenance Project Description Estimated Project Cost
Resurfacing Milling,patching,leveling,and resurfacing of approximately 7 additional miles $16,435,000
of roadway per year based upon the PACERS Rating System.
Maintenance Seal Coat 8 Miles per year based upon the PACERS Rating System $1,680,000
10%Project Contingency $1,811,500
Road Resurfacing/Maintenance Estimated Total Costs $19,926,500
Tier 1 Multi-use Pathway System tunnel and bridge maintenance projects included:
Pathways Tunnel and Bridge Maintenance
Project Estimated Project Cost
Project Description
Costs Based on 2016 Competitive Bid Process $700,000
Pathway Repairs and Maintenance for eleven (111 Pathway Bridges: B14,B17,B28,
Bridges B23, B19,B24, B26,B03, B08,B21,and B27
Pathway Repair and Maintenance for seventeen (17) Pathway Tunnels: T19,T06,
Tunnels T10,T1 1,T16,T05,T02,103;104,108,T13,T20,T22,T24,T26,T28,T29
10%Project Contingency $70,000
Pathways Tunnel and Bridge Maintenance Estimated Total Costs $770,000
There had been a language change pertaining to the number of miles per year that Rorie said he
had changed from 12 miles per year to avoid any confusion — the SPLOST funds would fund three
miles per year in addition to the nine miles that would remain in the General Fund. Tier-1 projects
for path repair and maintenance included:
Project
City Wide
Multi-Use Paths Annual Repair and Maintenance Project Description Estimated Project Cost
Resurface an additional 3 Miles per year based on resurfacing schedule
based upon
rating allowing all paths to be resurfaced approximately every 8 years.
Equipment Purchases
750 Dump $90,000
350 Dump Truck $60,000
Asphalt Spreader $165,000
S-Bobcat $60,000
Root Cutter Machine $70,000
Supplies/Materials
Additional Supply Costs:Gravel and Asphalt($73,000 per mile X 3 Miles x 5 $1,095,000
Years)
Labor
1-Equipment Operator, 1-Truck Driver,and 3-Maintenance Techs x 5 Years $1,500,000
10%Project Contingency $304,000
Pathways Tunnel and Bridge Maintenance Estimated Total Costs $3,344,000
Some projects were moved to Tier 2, including a bridge at Crosstown/SR 74 and another bridge on
SR 74 in the Westpark Walk/Smokey Bones area. One path was removed because it was not
considered feasible since the Georgia Department of Transportation would not give a permit for a
multi-use path in the right-of-way. Multi-use Path Access and Connectivity Enhancements
included:
Project Pathways Access and Connectivity Enhancements Project Description Estimated Project Cost
Pathway Addition SR 54 E(Peachtree East to PTC United Methodist Church $88 000
(Master Plan 10& 11)
Bridge Addition SR 54 W multi-use bridge and gateway feature(Master Plan Project#54) $1,971,000
Pathway Addition N Peachtree Parkway Path $215,000
City Council Workshop Minutes
June 7,2016
Page 7
Pathway Addition Flat Creek Nature Area (PAC/MOBA to Crosstown Drive Master Plan#26) $217,227
Pathway Addition North Peachtree Pkwy(Flat Creek Rd connection-Master Plan Project#14) $42,712
Pathway Addition Crosstown Dr.Crossing(Master Plan Project#24) $26,993
Pathway Addition Robinson Road-Whitfield Farms connection (Master Plan Project# 15) $132,000
Pathway Addition Crosstown Drive(Wendy's connection-Master Plan Project#25) $7,080
Pathway Addition Paschall Rd(Master Plan Project#48) $42,260
Pathway Addition Huddleston Road (Master Plan Project# 50) $206,000
Pathway Addition Cedarcroft to 74 Bridge Path via long drainage easement adjacent to $209,000
MacDuff
Pathway Addition Walt Banks and N.Peachtree Pkwy to Kedron Crossing $300,000
10%Project Contingency $344,827
Pathways Access and Connectivity Enhancements Estimated Total Cost $3,793,099
Rorie said the Lake Peachtree Spillway/Dam Enhancements were programmed at $2.2 million, and
the focus was what to do to upgrade the dam to Category 1. Additional funding for Lake
Peachtree included:
Project Lake Peachtree Spillway/Dam Enhancements Project Description Estimated Cost
Lake Peachtree Spillway Replace Spillway to meet Category 1 Standards $1,000,000
Lake Peachtree Dam Upgrade Dam to meet Category 1 Dam Upgrade $1,000,000
10%Project Contingency $200,000
Spillway/Dam Estimated Total Cost $2,200,000
Tier 2 projects included two intersection projects. Rorie said there were no engineering plans for the
projects yet. Putting the projects in Tier 2 would provide time for an assessment. The additional
path and bridge projects were moved from Tier 1 to Tier 2 in the event there would be funding
available. Some additional surfacing and maintenance was also added to Tier 2. Tier 2 projects
included:
Tier 2
Estimated
Transportation
Project Cost
SR 54 @ Add left turn lane extension and restrict left turn movements into and out of $150,000
Commerce Drive Commerce Drive
SR 74 @
S.Kedron Dr Convert to right-in and right out only from S.Kedron Drive $30,000
Additional Road Resurfacing/Maintenance $2,000,000
Multi-Use Path Access and Connectivity Enhancements Project Description
Bridge Addition HWY 54/74 Gateway Bridge(Access Avenue to West Park) CorkScrew?Location $1,971,000
Bridge Addition Hwy 74/Crosstown Bridge/Tunnel $1,971,000
Pathway Addition Police Station( ) $51,523
Pathway Addition Kedron Village retail path relocation(Master Plan Project#3) $18,195
Pathway Addition Robinson Road (Camp Creek Estates connection-(Master Plan Project#18) $80,926
Pathway Addition North Kedron Dr.Extension(Master Plan Project#58) $25,523
Pathway Addition SR 54 E/Lake Peachtree multi-use bridge replacement(Master Plan Project#16) $539,000
Pathway Addition Robinson Road SCrosstown Dr connection(Master Plan Project#19) $125,850
Pathway Addition Crosstown Business Park(Master Plan Project#21) $72,628
Pathway Addition Holly Grove Road (Master Plan Project#35) $69,282
Pathway Addition Robinson Road (The Summit connection(Master Plan Protect#28) $70,357
Pathway Addition Line Greek Nature Area (Master Plan Project#53) $44,233
Total Tier 2 Cost Estimate $7,219,517
City Council Workshop Minutes
June 7,2016
Page 8
Rorie said the "Lazy River" project had been removed, saying the estimated cost was too low. Staff
had gotten two quotes, ranging from $250,000 to $500,000. The recommendation had been to
remove mobile restrooms and put them in the Public Improvement Program (PIP), and that
adjustment had been made. Projects considered for elimination included:
Elimination
Project Parks and Recreation Estimated
Project Cost
Glenloch Recreation Addition of"Lazy River" feature to Glenloch Recreational Pool $150,000
Mobile Facility Mobile Restroom to facilitate Special Events $35,000
Transportation
N.Peachtree Pkwy @ Install traffic calming devices at N.Peachtree Pkwy/Loring Lane and $950,000
Loring Lane/Tinsley Mill N.Peachtree Pkwy/Tinsley Mill
Pathways
Pathway Addition SR 74 South (Phase I Master Plan Project#41) $444,170
Total Reduction from Estimated Cost $1,579,170
Rorie reiterated the numbers used in the funding model were estimates. Currently, there were
$2,578,908 in undesignated funds. He planned to present the finalized list to Council on the June 16
agenda. The new funding model included:
Peachtree City 2016 SPLOST
Projected Sales Tax Collections $37,580,607
Public Safety $2,130,100
Parks and Recreation $1,023,000
Transportation $22,291,500
Multi-Use Pathway System $7,907,099
Cat I Dam/Spillway Enhancements $1,650,000
Total Estimated Costs$35,001,699
Un-designated $2,578,908
Tier 2 Projects $7,219,517
Rorie continued that the City could not market a "yes" or "no" vote in support of SPLOST, but timely
information could be provided to citizens. Staff was working on a package that would be
available on the website and in paper at various City facilities. There would be maps showing the
proposed multi-use path connections. He continued that Fayetteville had already adopted a
project list, and the County was working on theirs. They were also waiting to find out if it would be a
five- or six-year SPLOST.
Learnard referred to the list of path projects, saying she did not know what Master Plan Project #15
was. She thought Council would be done with the SPLOST list at this meeting, and there would be a
map with all path projects shown. She thought they should be working on priorities, asking if the lists
were in priority order. Rorie said they were all priority projects, but were not in numerical order.
Learnard asked if they were going to prioritize the projects. Rorie said they were Tier 1 projects and
would be done over a five to 10-year period. Learnard said not all the projects would get done.
Rorie said all the projects on the list would get done,-and he would not make a recommendation
for a Tier 1 that could not be done in that time period.
Learnard said she did not know, for example, what they were saying when the project was listed as
"Paschall Rd (Master Plan Project #48)" or what was being connected. Rorie said that was the
point of the presentation. When the project list was put together, they would be shown on a map
with the name and project number. He did not have that at this meeting. Ernst said Council was
being asked if they accepted the list. If they did, then Rorie would do that.
City Council Workshop Minutes
June 7,2016
Page 9
Learnard asked, if SPLOST were to pass, would the City start with a practical implementation. Rorie
said staff would start the projects immediately. Learnard said they could not all be done in the first
year. Rorie referred to SR-54 W multi-use bridge and gateway feature (Master Plan Project #54),
saying that project should not be done in year one, when engineering, design, and permitting had
to be completed. The projects had to be timed, and other projects could be completed while the
engineering, design, and permitting were being done.
Caren Russell said the idea of an information packet was wonderful for the website. It was very
important to get the SPLOST passed. She suggested calling it a "resident information initiative," and
to get the newspapers involved, to,get the word out to the public. A public meeting should be
held before the vote to answer questions. People needed to know a SPLOST was the cheapest
way for residents, and non-residents, to pay for this. Publicity and education were hugely
important.
Learnard said just as there was a link to the City's website, there should also be a link to the County
website, so everyone could see all the projects laid out for the entire County. Rorie said it would be
important to inform the public, but there was a limit to what the City could do. They had to know
what the project focus would be. The information had to get out across all the communities and let
everyone know what they would be voting for or against. Staff would do what they could within
the limitations of the law.
Pam Kemp said she felt an urgency to get the information out about all the work that was needed
on all the roads, and the word needed to get out that an FDR was much more expensive than
regular paving. Rorie said the City's most valuable asset was its roads at an estimated $80 million. If
that asset was not repaired and maintained every year, it declined in value. It would cost more
down the road, as well as the decline in the value of the asset.
Larry Milligan said there were a lot of older people in the City who were not computer literate, and
they needed printed material. It should be made available, and she emphasized that they all
voted. Rorie said they were looking at a booklet as well as tri-fold brochures that would be
available at City facilities.
Prebor asked how the City could market the SPLOST information. Learnard said the City could
inform voters. Rorie said there could be town hall meetings. The media could be involved. Some
things could be done with social media and through UPDATES. Council could not say whether
citizens should vote yes or no. Prebor asked if any of the funds spent on getting the information out
could be budgeted. Rorie said no public money could be spent on getting the information out.
There had been discussions with the Chamber of Commerce as a third party, but the City could not
give them money to do it.
Michael Britt noted that residents paid a lot in stormwater fees, yet there were not stormwater
projects on the list. Rorie said the City had stormwater utility, which kept those funds out of the tax
base. It was an enterprise fund, adding there had been a debate on whether to use a utility or to
have stormwater as part of the General Fund. Britt asked what the SPLOST would cost the average
citizen. Rorie said it would be one cent on every dollar spent, adding that Fayette County was one
of.the few counties in Georgia that did riot have a SPLOST.
Russell suggested hold meetings with homeowners associations, saying it might be more effective
than trying to hold a large meeting few would attend.
City Council Workshop Minutes
June 7,2016
Page 10
Fleisch asked about changing the name of Snake Island and what deed restrictions could be
placed on the island. Rorie said it would be done internally. Someone had suggested a "name
that island" contest. He continued that City Attorney Ted Meeker had followed up and said the
City could add a deed restriction regarding the scope for a passive park.
Eric lmker addressed Council regarding the proposed SPLOST, saying everything about it was good
news. He assumed the SPLOST would be five years, adding that the General Fund would add $1.8
million per year (generating $9 million over five years) for roads and $1.7 million per year
(generating $8.5 million over five years) to the SPLOST total. Imker said that would give the City $55
million to work with on the infrastructure. He asked Council to consider a one mill decrease ($9
million) in the property tax,which would leave $45 million for roads and paths. If the SPLOST was not
approved by the voters, the City could not re-designate the millage funds ($17.5 million over five
years) for roads and paths to something else. It had to be left in the budget for that purpose. lmker
said that was what happened with the 2005 SPLOST. Council decided to use the money in the
General Fund for something besides roads and paths. lmker said that caused a huge $20 million
problem for the City.
Imker continued that he had e-mailed the week before the meeting, saying an option should never
be deleted from the list, but should be moved to Tier 2 in the event money came in than expected.
If it was not on the list, SPLOST funds could not be used. It was fine to use SPLOST for cart path labor.
He suggested using the undesignated funds for additional road and path maintenance in Tier 2.
Prebor noted that the proposal was to use the undesignated funds as the City's contribution to the
performing arts center. Rorie confirmed that.
Imker continued that half the roads in the City would be touched by the SPLOST over five years,
adding that everyone drove and knew lots of repairs were needed. He pointed out two items on
the Recreation list had been eliminated ("lazy river" at Glenloch and mobile restrooms for special
events). He said that was the absolutely wrong to do things with the General Fund if SPLOST dollars
could be used. All projects should be moved to the Tier 2 list rather than eliminated. He
recommended adding $1 million to Tier 2 to purchase vehicles for the Fire Department and Police
Department rather than using bonds, which would save the City money on debt payments each
year. Learnard asked if that should be considered if the SPLOST were to go six years. Imker said if it
went for six years, the funding for the items should- be increased. The County did not have to
commit to the SPLOST until 30 days before the election. In early October, everything had to
identified, so the County had plenty of time to decide on a five-or six-year SPLOST.
Imker said the Category 1 dam/spillway was now listed properly. He liked using the term
"investment" for Recreation projects, rather than "amenity." Citizen input was needed for the Lake
Peachtree island; as well as from all citizens regarding any of the projects. He noted the proposed
bridge on the island had been shown on the south end, but Imker felt the passive park should be on
the north end. Learnard said that was a good point, and Council should also discuss a golf cart
parking area wherever the bridge would be located, especially if it was exclusively a pedestrian
bridge. Parking should be included, Learnard said, adding that there could be issues on the Fourth
of July if a lot of people wanted to watch fireworks from the island. Rorie agreed.
Imker said two items on the "Elimination List" should be moved to Tier 2, especially the mobile
restroom. He referred to the discussion at the June 2 Council meeting where Rorie and Council said
the project could be moved to the General Fund. Imker said that was the wrong approach.
General Fund money should not be used for something when SPLOST funds could be used.
General Fund money could be used for anything, but SPLOST money had to be used to fund things
on the list.
City Council Workshop Minutes
June 7,2016
Page 11
Imker noted the SPLOST rules, saying these rules were "super generalized:"
• Allowed to shift funds between projects, but all Tier 1 projects must be completed unless
money runs out. Funds must be guaranteed to run out, [or] else...
• Funds must be returned to County to reduce debt, reduce ad valorem taxes, or both.
• How guaranteed to run out? Answer - Tier 2 Projects funded or additional funds to Tier l
projects (Example: path/road maintenance).
Imker briefly discussed how "to sell" the SPLOST. He referred to a map that visually showed where
the SPLOST funds would go in the County, which showed how the money was distributed to the
municipalities. Imker said he would be the spokesman for SPLOST, and he would personally tell
people to vote for it. He continued that only one of the last four SPLOST attempts had been
approved by the voters, and it was only by the narrowest of margins. SPLOST referendums were
defeated in 2010, 2012 (a transportation SPLOST for the Atlanta region), and 2014. lmker noted that
the City would do what it wanted with its share of the money, as would the County and the other
municipalities. According to lmker, City voters had not understood how the City would benefit from
approval of the previous SPLOST referendums.
Imker continued that if a one mill (approximately $100 - $125) reduction in the City's property tax
was included with the information given to voters, he believed residents would vote for approval.
The actual cost of the SPLOST to a resident might be $150, depending on spending habits. Using
SPLOST to pay for Public Services vehicles and, equipment would save the City approximately
$250,000 per year for principal and interest payments for each $1 million in loans for the equipment.
If two loans were going simultaneously (two $1 million loans), it would account for the other $25
spent for the additional one cent sales tax. The one mill decrease would mean City taxpayers
would not be paying anything out of pocket if the SPLOST were approved. It was essentially a
break even proposition. There should be a non-binding recommendation to decrease the millage
rate for the next year.
Learnard asked when he was proposing the one mill decrease be done. Imker said it should be for
the 2017 tax bills or the FY 2018 budget.
Hayes questioned where the money would come from if there would be no cost to the residents,
adding she was unfamiliar with the details of the SPLOST. Learnard explained that instead of
paying 6% on purchases at the local shopping areas, people would pay an extra penny, or 7%. The
pennies added up, and they went back to the County. The County would distribute the pennies
collected based on a formula, based on population and the current LOST distribution. All shoppers,
including those from outside the County, would pay 7%in sales tax. Every year that Fayette did not
have a SPLOST and the neighboring counties did, Fayette residents were paying into the coffers of
other counties, while their residents did not pay into Fayette County's. Learnard continued that
Imker said rolling back the property tax would break even. (More explanation was given to Hayes
regarding the SPLOST and how it worked, but no one used the microphone.)
Rorie said staff had looked at three locations for the pedestrian bridge to the island and had
spoken to the residents who lived in the area. Basically the island and area along the shoreline
were all wetlands. There were strong objections to building a pedestrian bridge on the north end of
the isFand and its impact on the wetlands. There would be less impact on the neighbors-and the
wetlands if something was done on the south end of the island, but the distance would be greater.
City property was also available on the south end that could be utilized for parking golf carts.
Jay Scheibler said he had not realized there was so much City-owned land on the south end for
parking. If the bridge was on the extreme north end, a longer bridge would be needed, but there
City Council Workshop Minutes
June 7,2016
Page 12
was a parking lot nearby. Learnard said there would be parking for the golf carts there. Fleisch
and King both noted the parking would be limited. King continued that Council could make the
decision on where to put the bridge during the five-year period of the SPLOST, so he did not see a
reason to get "wrapped around this axle." Learnard said she was not convinced it was needed at
all. She pointed out that the City would have to maintain a passive park, provide parking, and pick
up trash. It would be an ongoing expense, asking why it was a good idea.
Imker, who also served on the Infrastructure Advisory Group, said he did not think any Battery Way
residents had been a part of the group, but he understood King's point. This could be a Tier 2
project and discussed later. Learnard said she could support that. Prebor said they would have to
get through all the Tier 1 projects first, and they could prioritize it later if it was in Tier 2. King and
Ernst said they did not have any issue with doing that.
Marcia Brown, noting she lived on Battery Way, told Council she was very passionate about the
wetlands remaining wetlands. She liked the idea of moving the project for the island to Tier 2 so
there would be more time to look at everything. A cost of a 100-foot wooden bridge would be
quite a bit. There was still a lot of undergrowth on the island, as well as an overabundance of deer
because there were no predators on the island, which created problems for the lake. Teenagers
liked to go to the island and drink because the underbrush provided a nice screen. She recalled
that Rorie had mentioned clearing the underbrush and leaving the trees, which would become
self-renewing and would not involve a lot of labor for Public Works once the underbrush was gone.
She asked Council to consider that before the passive park. Brown asked that Council remember
their homes were behind the island, and anything the City did would have a direct impact on their
home values, including the drop in the home values when the island had been put in place and
they lost their lake view.
Debbie Britt said the- same- problems would exist if the island' were located anywhere else..
Undesirable things happened on the island, and Council should consider what the cost would be if
nothing was done. They recognized it was a community issue. The projects on the SPLOST list must
be something that would resonate with everyone. The island had been a topic of discussion for a
long time, and while $200,000 was a lot of money, in the scheme of $30 million plus, she saw no
reason to move the project to Tier 2. If they compromised now, there might not be another shot to
fix it.
Fleisch asked if the bridge had to be located to keep the project in Tier 1. Rorie said it did not, but
they would need to clearly indicate what the scope of the project was. They could clear the
underbrush and leave the specimen trees, even if there was not a bridge to the island. Nothing had
been done in 30 years. Fleisch noted the island had been there since 1986 and the estimate to
clear the island was $176,000. Rorie said it needed to be adequately funded. Fleisch said the
estimate for the land bridge, which would not work, and the clearing was approximately $400,000.
Rorie said there were three price points for the work, ranging from $200,000 to $700,000 (which
included electricity, etc.). There were some compromises that could be made on the scope. Ernst
said to leave it in Tier 1 and add another $200,000 (total $400,000) to fund removal of the
underbrush.
Learnard said it made sense to move the mobile restroom and $1 million for Public Safety vehicles
to Tier 2. Rorie said the mobile restrooms had been moved to the Public Improvement Program
(PIP) in the budget. Fleisch said she would like to add funds to the PIP to put in wires and street
lights at the intersections on SR 54 at Walt Banks, Robinson Road, Peachtree Parkway, and Prime
Point, saying when the poles were in, there were not street lights. The estimate was $55,000 -
City Council Workshop Minutes
June 7,2016
Page 13
$65,000 to do that. Learnard asked if some of the items in the PIP could go on the SPLOST list. Rorie
said they could.
Learnard asked what would happen if the County decided on a six-year SPLOST. Rorie said they
could expand some of the cart path projects and add more funding to the resurfacing program on
an annual basis. It would just be another year of funding. Learnard said there were other projects
that could be added, saying that was another reason to put the police vehicles on Tier 2. Rorie
said there was still time to make that decision. The first thing they needed to know was how long
the SPLOST would be, and then it would easy to clean things up and put in some additional Tier 2
projects.
Ernst said there were not any police vehicles on the list. King asked that police vehicles not be
included on the SPLOST list, as voters might vote it down. People looked at this as a "special" Local
Option Sales Tax (LOST), and they would vote it down it there were items that should be funded by
operational funds. That was one of the concerns with the SPLOSTs that had failed. He wanted to
support this SPLOST, but he had concerns when operational items were included. A consensus of
Council agreed.
Rorie said he would present the list for final approval on June 16. Learnard said she was ready to
see the map with all the projects shown on it, and she thought they would be looking at the final list
at this meeting. . Rorie said he had needed the list to move forward with that detail. He would not
engage other staff members to come up with that information unless it was on the list. There were
56 projects on the cart path master plan, and Rorie said the list had to be narrowed down so
attention could be focused on those projects. Learnard asked if that had been done. Rorie said
he hoped it had. Learnard said she still did not know what Master Plan #48 meant. Learnard asked
Rorie to clarify that a map would not be ready until the projects were approved. Rorie said he
understood her point, but he could not see doing all the work that had been done, only to tear it
down.
Ernst recommended Rorie and staff move forward with the list as presented. The other members
agreed.
• City Council Goals and Objectives-FY2016 Prioritization Finale
Rorie noted Council had given staff a list of goals to work on. Some had been completed and
some had been-tweaked. It was an ongoing process.
Rorie continued that Executive Assistant Debbie Lemay coordinated a survey with other Class B
cities. The cities were asked what their millage rates were, and the list included the City (6.756 mills),
Douglasville (7.338 mills), Duluth (5.991 mills), Gainesville (1.75 mills), Hinesville (11.51 mills), Kennesaw
(8 mills), Lawrenceville (2.025 mills), Newnan (4.05 mills), Rome (6.8 mills), Statesboro (6.358 mills), and
Dalton (2.511 mills). Duluth used SPLOST to help support their budget. Gainesville had a low millage
rate, but it was based on 100% of. value rather than 400, and they had SPLOST funds.
Lawrenceville, Kennesaw, Newnan, Rome, Statesboro, and Dalton also had SPLOST funds. Only
Peachtree City and Hinesville did not have any SPLOST funds.
Rorie continued that the cities did not have all the same responsibilities. The big three were Public
Works, Fire, and Police in any budget as they were capital and labor intensive. Douglasville, Duluth,
Kennesaw, Lawrenceville, and Stockbridge were covered by their county's Fire Departments.
Police and Public Works were included in all the cities' budgets. Recreation was either not
covered, covered by the county, or had nothing in the budget in Hinesville, LaGrange,
Lawrenceville, Newnan, Rome, and Statesboro. Peachtree City, Hinesville, Newnan, and Dalton
City Council Workshop Minutes
June 7,2016
Page 14
were the only cities to fund libraries. Peachtree City, Rome, and Statesboro were the only cities
that had a Senior Center.
Rorie continued that each city also spent different amounts for Police and Public Works. He noted
that Douglasville spent $1,674,842 on Public Works compared to $7,693,120 for Peachtree City, but
Douglasville probably did not have 471 subdivision entrances and islands to maintain or 90-plus
miles of cart paths. There were also big differences in amounts spent on Recreation and a Senior
Center.
Rorie pointed out there was also a difference in numbers of employees. The City had 250 full-time
and 106 part-time employees. Stockbridge had 70 full-time employees. Some cities had a bigger
population, while other cities had more square miles than Peachtree City. Gainesville had 670 full-
time employees and 32 part-time. The City tried to do a lot more with part-time employees than
others did.
Rorie then gave an update on the following:
2015 Ongoing Goals and Objectives
Objective Time Who Progress
1 Dredge Lake Peachtree 6 months Council Complete-Finally
2 Upgrade Battery Way Dock infrastructure 6-12 months Jim Pennington Underway-Bollards by
Staff-Deck Seal
3 Examine funding options for path work(how to obtain Council/Staff Registration Fee increases,
funds,not how to spend the funds) Milloge Increases,and
SPLOST initiative during 12-
1-15 CC Workshop also
exploring grant potential
4 Develop long-term plan for City Center Parks (including 2 years Council Underway Water
City Hall Plaza,Drake Field and connection to All installed,Grass is growing
Childrens Playground, Battery Way Park,Island and but electrical requires
restrooms) Georgia Power boring to
complete electrical
5 Review/finalize organizational structure (Public Works and 6-12 months Council/City Mgr Under review
Community Services)
6 Improve access for carts crossing Crosstown Drive 12-18 months Staff/DOT GDOT denied at grade
crossing on HWY 74,plans
have been developed for
North to South Crossing
across Crosstown.$300K+
funding unavailable
7 Extend Right turn lane coming out of Planterra onto SR 54 12-18 months Council/ Engineer Plans
Engineering completed-will need to
acquire easements($430
to$490K)
9 Evaluate North Lagoon of Lake Peachtree-Dredging? 6-12 months Engineering ISE Task Order to explore
Siltation sources?Silt collector?Ownership? options
12 Complete an inventory of City-owned sewer lines and lift 6 months Staff Currently underway-
stations to convey to WASA inventory being
completed
13 Determine Optimal maintenance costs for normal levels on-going Council/Staff Depends on road
of service resurfacing and cart path
plans
Rorie continued that staff was reviewing employee benefits and were looking at different options,
and the discussion would continue during the workshop on the FY 2017 budget discussions. The list
going forward included:
City Council Workshop Minutes
June 7,2016
Page 15
Going Forward
Obiecti�e Time Who Progress
1 Connect annexed areas to path system (Publix East) 12-15 months Council/Public Works SPLOST Initiative
4 Evaluate expanding transportation options for Council
Peachtree City Seniors
6 Review employee benefits including Defined Benefit on-going Council/Staff Ongoing-FY 2017
vs 457 Plan Budget discussion
Rorie said Council should let staff know about anything else they wanted to include. Prebor said
they had discussed a "communications" employee, asking if that employee was included. Rorie
said there was a placeholder in the draft budget so it would be discussed during the budget
workshops.
The workshop concluded at 9:12 p.m.
421416t6J -
1111
Pamela Dufresne, Dep City Clerk Vanessa Fleisch, Mayor